Programs Database ProjectAction Plan
- Updated 6/20/01
|
What
|
Who
|
By When
|
Done?
|
Task 1 - Distribute database & on-line data entry forms to all centers. |
Fernando
|
6/21/01
|
X
|
Task 2 - Centers enter national organizations for topic hub use and regional programs. |
All
|
7/15/01
|
on-going
|
Task 3 - Centers check in on progress, problems, etc. during a regularly scheduled web call. |
All
|
July
|
X
|
Part 2 - Regional Program Directories
What
|
Who
|
By When
|
Done?
|
Task 1 - Interested Centers meet to discuss on-line reports (announcement on the list serve). |
Fernando & Laura
|
7/6/01
|
X
|
Task 2 - Further revise Use Guide to reflect enhancements, and "hot button" issues (Scope of Data, Validation, Keywords Allowance). |
Laura
|
7/6/01
|
X
|
Task 3 - Centers review Use Guide and submit comments to Laura. |
All
|
7/30/01
|
|
Task 4 - Conference call to demonstrate how Program Directories appear on regional sites, exchange coding among Centers. |
Volunteers
|
8/30/01
|
|
Task 5 - Regional Programs Directory exists (in some form) on all Centers' sites. |
All
|
9/30/01
|
|
Part 3 - National P2Rx Programs Directory
What
|
Who
|
By When
|
Done?
|
Task 1 - Visioning the National Programs Directory Some issues: content sharing, maintenance, quality control, appearance, administrative tools, self-entry of data (It is anticipated that this discussion will generate several additional task lists.) |
All
|
9/15/01*
|
|
Task 2 - Decide URL(s) for initial launch of the product and roll out strategy. |
All
|
9/15/01
|
|
Task 3 - Write functional spec. |
Volunteers
|
10/30/01
|
|
Task 4 - Approve functional spec and determine resources needed and available. |
All
|
11/15/01
|
|
Task 5 - Obtain resources needed and begin implementation by generating new task list. |
All
|
12/30/01
|
|
*workloads permitting