      Programs Database ProjectAction Plan 
        - Updated 6/20/01
       | 
  
|  
             What 
           | 
           
             Who 
           | 
           
             By When 
           | 
           
             Done? 
           | 
        
| Task 1 - Distribute database & on-line data entry forms to all centers. |  
             Fernando 
           | 
           
             6/21/01 
           | 
           
             X 
           | 
        
| Task 2 - Centers enter national organizations for topic hub use and regional programs. |  
             All 
           | 
           
             7/15/01 
           | 
           
             on-going 
           | 
        
| Task 3 - Centers check in on progress, problems, etc. during a regularly scheduled web call. |  
             All 
           | 
           
             July 
           | 
           
             X 
           | 
        
        Part 2 - Regional Program Directories
|  
             What 
           | 
           
             Who 
           | 
           
             By When 
           | 
           
             Done? 
           | 
        
| Task 1 - Interested Centers meet to discuss on-line reports (announcement on the list serve). |  
             Fernando & Laura 
           | 
           
             7/6/01 
           | 
           
             X 
           | 
        
| Task 2 - Further revise Use Guide to reflect enhancements, and "hot button" issues (Scope of Data, Validation, Keywords Allowance). |  
             Laura 
           | 
           
             7/6/01 
           | 
           
             X 
           | 
        
| Task 3 - Centers review Use Guide and submit comments to Laura. |  
             All 
           | 
           
             7/30/01 
           | 
          |
| Task 4 - Conference call to demonstrate how Program Directories appear on regional sites, exchange coding among Centers. |  
             Volunteers 
           | 
           
             8/30/01 
           | 
           
             | 
        
| Task 5 - Regional Programs Directory exists (in some form) on all Centers' sites. |  
             All 
           | 
           
             9/30/01 
           | 
           
             | 
        
Part 3 - National P2Rx Programs Directory
|  
             What 
           | 
           
             Who 
           | 
           
             By When 
           | 
           
             Done? 
           | 
        
| Task 1 - Visioning the National Programs Directory Some issues: content sharing, maintenance, quality control, appearance, administrative tools, self-entry of data (It is anticipated that this discussion will generate several additional task lists.) |  
             All 
           | 
           
             9/15/01* 
           | 
           
             | 
        
| Task 2 - Decide URL(s) for initial launch of the product and roll out strategy. |  
             All 
           | 
           
             9/15/01 
           | 
          |
| Task 3 - Write functional spec. |  
             Volunteers 
           | 
           
             10/30/01 
           | 
          |
| Task 4 - Approve functional spec and determine resources needed and available. |  
             All 
           | 
           
             11/15/01 
           | 
           
             | 
        
| Task 5 - Obtain resources needed and begin implementation by generating new task list. |  
             All 
           | 
           
             12/30/01 
           | 
           
             | 
        
*workloads permitting